Column 1
|
Column 2
|
Proposed development
|
Qualifying criteria
|
1 Agriculture
|
(1) To
change the use of uncultivated or semi-natural land to use for an intensive
agricultural purpose.
|
The area of the
land exceeds 0.5 hectares.
|
(2) To
develop a water-management project for agriculture, including irrigation or
land drainage project.
|
The area of the
project exceeds 0.5 hectares.
|
(3) To
construct or install an intensive livestock installation.
|
The area of the
installation exceeds 0.5 hectares.
|
(4) To
develop or construct an installation to rear of fish.
|
The area of the
installation exceeds 0.5 hectares.
|
2 Extractive industry
|
(1) To
extract peat.
|
|
(2) To
carry out deep drilling, including, in particular –
(a) geothermal
drilling,
(b) drilling
for the storage of nuclear waste material,
(c) drilling
for water supplies,
but excluding drilling to investigate the
stability of the soil.
|
|
(3) To
extract minerals (other than metalliferous and energy-producing minerals)
including, in particular, marble, sand, gravel, shale, salt, phosphates and
potash.
|
|
(4) To
extract coal or lignite, whether by underground or open-cast mining.
|
|
(5) To
extract petroleum.
|
|
(6) To
extract natural gas.
|
|
(7) To
extract ores.
|
|
(8) To
extract bituminous shale.
|
|
(9) To
extract minerals (other than metalliferous and energy-producing minerals) by
open-cast mining.
|
|
(10) To
extract minerals by fluvial or marine dredging, except maintenance dredging.
|
|
(11) To
develop a surface industrial installation for the extraction of coal,
petroleum, natural gas or ores or bituminous shale.
|
|
(12) To
install a coke oven for the dry distillation of coal.
|
|
(13) To
construct an installation for the manufacture of cement.
|
|
3 Energy industry
|
(1) To
construct a power station or an installation for the production of
electricity, steam or hot water, not being a domestic scale solar panel or
wind turbine.
|
|
(2) To
construct an industrial installation –
(a) to
carry gas, steam or hot water; or
(b) to
transmit electrical energy by overhead cables.
|
|
(3) To
construct an installation for the surface storage of natural gas.
|
(1) The
area of any new building or structure exceeds 500 square metres.
(2) The
installation will be sited within 100 metres of a stream, pond or reservoir.
|
(4) To
store combustible gas underground.
|
(1) The
area of any new building or structure or of the storage area exceed 500
square metres.
(2) The
storage area will be sited within 100 metres of a stream, pond or reservoir.
|
(5) The
surface storage of fossil fuel.
|
(1) The
area of any new building or structure, or of the deposit exceed 500 square
metres.
(2) The
deposit will be sited within 100 metres of a stream, pond or reservoir.
|
(6) The
provision of an installation for the industrial briquetting of coal or
lignite.
|
|
(7) The
construction or change of use of an installation for the production or
enrichment of nuclear fuels.
|
|
(8) The
construction or change of use of an installation for the reprocessing of
irradiated nuclear fuels.
|
|
(9) The
construction or change of use of an installation for the collection or
processing of radioactive waste.
|
|
4 Production and
processing of metals
|
(1) The
construction of an ironworks or steelworks, including a foundry, forge,
drawing plant or rolling mill.
|
|
(2) The
construction or change of use of an installation for the production
(including smelting, refining, drawing and rolling) of non-ferrous metals,
other than precious metals.
|
|
(3) The
construction or change of use of an installation for the pressing, drawing or
stamping of large castings.
|
|
(4) The
construction or change of use of an installation for the surface treatment
and coating of metals.
|
|
(5) The
construction or change of use of an installation for boilermaking or
manufacturing reservoirs, tanks and other sheet-metal containers.
|
|
(6) The
construction or change of use of an installation for manufacturing or
assembling motor vehicles or manufacturing motor-vehicle engines.
|
|
(7) The
construction or change of use of an installation for use as a shipyard.
|
|
(8) The
construction or change of use of an installation for the construction or
repair of aircraft.
|
|
(9) The
construction or change of use of an installation for the manufacture of
railway equipment.
|
|
(10) The
construction or change of use of an installation for swaging by explosives.
|
|
(11) The
construction or change of use of an installation for roasting or sintering
metallic ores.
|
|
5 Glass making
|
The
construction or change of use of an installation for the manufacture of
glass.
|
|
6 Chemical industry
|
(1) The
construction or change of use of an installation for the treatment of
intermediate products and the production of chemicals.
|
|
(2) The
construction or change of use of an installation for the production of
pesticides or pharmaceutical products, paints or varnishes, elastomers or
peroxides.
|
|
(3) The
construction or change of use of an installation for the storage of petroleum
or petrochemical or chemical products.
|
|
7 Food industry
|
(1) The
construction or change of use of an installation for the manufacture of
vegetable or animal oils or fats.
|
The new floor area
of the installation exceeds 1000 square metres.
|
(2) The
construction or change of use of an installation for the packing or canning
of animal products.
|
The new floor area
of the installation exceeds 1000 square metres.
|
(3) The
construction or change of use of an installation for the manufacture of dairy
products.
|
The new floor area
of the installation exceeds 1000 square metres.
|
(4) The
construction or change of use of an installation for brewing or malting.
|
The new floor area
of the installation exceeds 1000 square metres.
|
(5) The
construction or change of use of an installation for confectionery or syrup
manufacture.
|
The new floor area
of the installation exceeds 1000 square metres.
|
(6) The
construction or change of use of an installation to be used to slaughter
animals.
|
The new floor area
of the installation exceeds 1000 square metres.
|
(7) The
construction or change of use of an installation to manufacture industrial
starch.
|
The new floor area
of the installation exceeds 1000 square metres.
|
(8) The
construction or change of use of an installation for use as a fish-meal or
fish-oil factory.
|
The new floor area
of the installation exceeds 1000 square metres.
|
(9) The
construction or change of use of an installation for use as a sugar factory.
|
The new floor area
of the installation exceeds 1000 square metres.
|
8 Textile, leather, wood
and paper industries
|
(1) The
construction or change of use of an installation for use as a wool scouring,
degreasing or bleaching factory.
|
The area of new
floor space of the installation exceeds 1000 square metres.
|
(2) The
construction or change of use of an installation to manufacture fibre board,
particle board or plywood.
|
The area of new
floor space of the installation exceeds 1000 square metres.
|
(3) The
construction or change of use of an installation to manufacture pulp, paper
or board.
|
The area of new floor space of the installation exceeds 1000
square metres.
|
(4) The
construction or change of use of an installation for use as a fibre-dyeing
factory.
|
The area of the
floor space of the installation exceeds 1000 square metres.
|
(5) The
construction or change of use of an installation for use as a
cellulose-processing or production installation.
|
The area of new
floor space of the installation exceeds 1000 square metres.
|
9 Rubber industry
|
The
construction or change of use of an installation to manufacture or treat elastomer-based
products.
|
|
10 Infrastructure
projects
|
(1) The
carrying out of an industrial estate development project.
|
The area of the
development exceeds 0.5 hectares.
|
(2) The
carrying out of an urban development project, including the construction of
shopping centres, car parks, sports stadiums, leisure centres and multiplex
cinemas.
|
Floor area of the
buildings included in the project exceeds 10,000 square metres.
|
(3) The
installation of a cable-car.
|
|
(4) The
construction of a road.
|
The area of the road,
including any pavements, exceeds 0.5 hectares.
|
(5) The
construction of a harbour, including a fishing harbour.
|
|
(6) The
construction of an airport.
|
|
(7) The
canalisation or flood-relief works.
|
The area of the
canal and any auxiliary work exceeds 0.5 hectares.
|
(8) The
construction of a dam or any other installation designed to hold water or
store it on a long-term basis.
|
The area of the
dam or installation exceeds 0.5 hectares.
|
(9) The
construction of a tramway, elevated or underground railway, suspended line or
similar line.
|
|
(10) The
construction of an oil or gas pipeline installation.
|
|
(11) The
installation of a long-distance cable for the transmission of electricity.
|
|
(12) The
construction of a long-distance aqueduct.
|
|
(13) The construction
of a marina.
|
|
(14) The
construction of coastal works to combat erosion, (but not the maintenance and
reconstruction of such works).
|
|
(15) The
construction or placing of maritime works that are capable of altering the
coast by virtue of their construction or placement.
|
|
11 Other projects
|
(1) The
construction of a holiday village or hotel complex and associated
developments in a rural location.
|
The area of the
development exceeds 0.5 hectares.
|
(2) The
construction of a permanent racing or test track for cars or motor cycles.
|
|
(3) The
laying out of a golf course and the construction of any associated
development.
|
The area of the
course and any associated development exceeds 0.5 hectares.
|
(4) The
construction of an installation for the disposal or treatment of waste
(including waste from mines and quarries and vegetable waste).
|
|
(5) The
construction of a waste water treatment plant, including a treatment plant
that forms part of any other development.
|
The area of the
plant exceeds 0.5 hectares.
|
(6) The
change of use of land to use as a site for the deposit of sludge (but not
treated or pelleted sludge).
|
|
(7) The
change of use of land to use as a site for the storage of scrap metal.
|
The land is within
100 metres of a stream, pond or reservoir.
|
(8) The
installation of a test bench for engines, turbines or reactors.
|
The area of new floor space of the development exceeds 1000 square
metres.
|
(9) The
construction or change of use of an installation to manufacture artificial
mineral fibres.
|
The area of new
floor space of the development exceeds 1000 square metres.
|
(10) The
construction or change of use of an installation to manufacture, package,
load or place in cartridges gunpowder or other explosives.
|
The area of new
floor space of the development exceeds 1000 square metres.
|
(11) The
construction or change of use of an installation or the change of use of land
for use as a knackers’ yard.
|
The area of new
floor space of the knackers’ yard exceeds 1000 square metres.
|
(12) Any
development on land covered or, in the normal course of tides, from time to
time covered by sea water.
|
|
(13) The
reclamation of land from the sea.
|
|